Production Calendar Auto-Scheduler
The Calendar places every active invoice on the days and hours your shop will work on it, one department at a time, earliest due date first. This guide covers how jobs are place...
Production Calendar Auto-Scheduler
The Calendar places every active invoice on the days and hours your shop will work on it, one department at a time, earliest due date first. This guide covers how jobs are placed and how to move them. Setting up departments and their hours is in the Production Capacity & Decoration Departments guide. Every button and field is listed in the Dashboard & Production Page Reference, section Production Calendar and capacity.
1. Feature Scope & UI Navigation
| What | Where |
|---|---|
| Calendar | Sidebar → Calendar, or click Unscheduled on a Dashboard job card |
| Unscheduled Queue | Calendar, Production view, left of the calendar (above it on smaller screens) |
| Production Schedule Workspace | Calendar → click a day |
| Shop hours | Finance & Settings → Financials → Operating Costs → Work Schedule & Capacity |
- Production shows the blocks on the days they are worked. Due Dates shows each invoice on its due date; you cannot drag there.
- Each day shows its hours booked and a capacity bar: green under 75%, amber from 75%, red at 100% or more.
2. Capabilities & Operational Boundaries
How it fits together:
- Each decoration's production time goes to its matrix's department.
- Jobs with a due date are placed for you, earliest due date first, starting today.
- Each department fills its own hours per day, then carries the rest to the next work day.
- The schedule re-packs by itself whenever due dates or jobs change. A job you drag to a day stays there for that department until you drag it somewhere else.
Boundaries:
- Only invoices are scheduled. Quotes, archived and rejected invoices, and invoices in a finished status never appear.
- The due date sets the order. It is not a deadline the schedule works back from, so a job can be placed after its own due date.
- Days before today are never used for jobs with a due date, even if the job is past due.
- Start times and Unschedule in the day window are saved only in the browser you used. Other people do not see them, and the capacity strip ignores them.
- Moving a job needs an active plan or trial. Without one the job jumps back.
3. Step-by-Step SOP Workflows
Let jobs schedule themselves
- Give the invoice a due date, on the quote or through Start the Due Date (Settings → Checkout & Payments → Turn Around Times & Rush Fees).
- The schedule saves when the invoice is saved, after a payment is recorded, and after a department sign-off changes.
Use the Unscheduled Queue
- Open Calendar in Production view.
- The Unscheduled Queue lists invoices with no due date and no production date. With none, the panel is hidden.
- Drag a job card onto a day. Its production date is set to that day at the shop's Start Time, and it goes onto the Calendar in every department it uses.
- Give a queued job a due date and it is placed for you instead.
Move a job to another day
- In Production view, drag a job block to a day.
- That department's part of the job starts there at the shop's Start Time. Hours that do not fit carry to the next work days.
- It saves right away. Other jobs in that lane move around it.
Set times in the Production Schedule Workspace
- Click a day to open the Production Schedule Workspace.
- Use Start Day At to start the whole day later. Work that no longer fits moves to the next work day.
- On a job card, drag the handle or pick a Time. A job can only be pushed later than the job ahead of it. Times taken in the same department show "(Occupied)".
- Click Unschedule to move a card into All-Day / Unassigned Time Slots. This does not change its date or free its hours.
- Use Set Time or the handle to put an All-Day job back, or Restore to return it to its planned time.
- Click Reschedule to apply Start Day At again and clear the day's own times.
4. Business Logic, Formulas & Rules
How a department is filled:
- Jobs you dragged to a day go first, in the order of their days. Then every other job with a due date, earliest due date first. Ties go by the lower quote number.
- Each job starts at the first free time in that department, from today at the shop's Start Time (or on its dragged day).
- It fills the day until the department's hours per day run out, then carries the rest to the next work day.
- The next job starts at the next free quarter hour after the one before it ends.
Rules:
- Each department's total for a job is rounded to the nearest 15 minutes, with at least 15 minutes.
- Outsourced jobs, and invoices with no decoration on a price matrix, get one 30-minute block in a lane called General.
- A department marked done in Department Sign-Offs no longer takes time. When every department is signed off, the job leaves the Calendar.
Screen print time = setup minutes × colors + run seconds × pieces × colors ÷ 60
Example: 3-color screen print, 100 shirts, Press Setup Time 10 minutes, Press Run Time 20 seconds.
- Setup = 10 × 3 = 30 minutes
- Run = 20 × 100 × 3 ÷ 60 = 100 minutes
- Total = 130 minutes, rounded to 135 minutes (2.25 hours)
Example: A job needs 6 hours in "Automatic Press 1", which has Hours per Day 4. The shop starts at 8:00 AM and works Monday to Friday. Today is Monday and the lane is empty.
- Monday: 8:00 AM to 12:00 PM, 4 hours (Day 1/2)
- Tuesday: 8:00 AM to 10:00 AM, 2 hours (Day 2/2)
- The next job in Automatic Press 1 starts Tuesday at 10:00 AM. Other departments are not affected.
- If the job were placed on a Friday, the rest would go to Monday, because Saturday and Sunday are not work days.
What changes the schedule:
- A due date moves: jobs you did not drag re-sort right away by the new due date. A department you dragged by hand stays where you put it. Start the Due Date counts calendar days, not work days.
- A department is signed off: its time is removed and the rest of the lane moves up.
- A job is finished, archived or rejected: it leaves the schedule and frees its time.
Staff and owner differences:
- Anyone who can open the Dashboard can drag jobs and set times.
- Staff whose View All Shop Jobs permission is off see "Personal Task Queue Active". The Calendar, its queue and the day window only show jobs assigned to them. The capacity strip still counts every job.
5. Troubleshooting & Diagnostic Matrix
| Symptom / Question | Root Cause | Exact Remediation Step |
|---|---|---|
| A job is not on the Calendar | It is still a quote, or it is archived, rejected or in a finished status. | Turn the quote into an invoice, for example by recording a payment. |
| A job is stuck in the Unscheduled Queue | Jobs in the queue have no due date. | Drag the job onto a day, or give it a due date. |
| A job is placed after its due date | The due date sets the order only; earlier-due jobs filled the lane first. | Drag it to an earlier day, or raise that department's Hours per Day. |
| A job I dragged went back to its old day | Moving needs an active plan or trial. | Check your subscription. |
| A coworker can't see the times I set | Start times and Unschedule are saved only in your browser. | Drag the job to a day instead; that saves for everyone. |
| A staff member sees only some jobs | Their View All Shop Jobs permission is off. | Turn it on in Settings → Staff/ Vendors → Edit Account, or assign them to the jobs. |
6. Frequently Asked Questions & Action Prompts
Why aren't my quotes on the Calendar?
Only invoices are scheduled. A quote shows up once it becomes an invoice and has a due date.
How does the schedule know how long a job takes?
From each decoration's quantity and its price matrix's production time fields. The minutes go to that matrix's department.
Can I move a job by hand?
Yes. Drag it to another day in Production view, or click a day and set its start time. It stays on that day until you drag it somewhere else.